'''List of Tasks & Leaders for Atlanta Preparations 2010''' | == '''List of Tasks & Leaders for Atlanta Preparations 2010''' == | ||
This is a list created to help us track the preparations for Atlanta. There is A LOT to be done, and we need everyone's help to do it. PLEASE pitch in and sign up for things if you haven't already. | |||
<br> | |||
'''Robot List''' | '''General List''' | ||
1. Fix Potentiometer | |||
2. Program Underglow - | 1. Unpack items from Boston - Jeff | ||
3. Autonomous Code for tower blocking - | |||
4. Manual Mode Lifter Code work - | 2. Repack items for Atlanta - Jeff | ||
5. Fix Welds on lifter - | |||
6. Make Second Lifter Structure - Amy Averill | 3. Video Tape the Chairmans Presentation - Shauna/Becca/Kyle | ||
4. Practice the Chairmans Presentation - Shauna/Becca/Kyle | |||
5. Thunderbolts - Kim | |||
6. Rookie Meet & Greet Booklet - Cynette <br> | |||
6a. Rookie Research - ?? | |||
7. Rookie Meet & Greet Planning - Cynette/Crystal/Lee | |||
8. Press Releases - ?? | |||
9. Sponsor Newsletter - Matthieu/Val Drake | |||
10. Sponsor Email - Val Drake | |||
11. Make More Buttons - Mrs. Wolf and all others welcome. | |||
12. Collect Boston Smugmug Photos - ?? | |||
13. Work on Scouting Laptops - Matthieu | |||
14. PRINT Pit Scouting & Match Prep Sheets - Kyle | |||
15. Make Master Schedule - Kim | |||
16. Coordinate Signups for Championship Conferences - ?? | |||
17. Update Robot Sheet - Kim | |||
18. New Chairmans Packets - Leann | |||
19. Prep for Atlanta PR presentation - Lee Drake/Crystal | |||
<br>'''Robot List''' | |||
1. Fix Potentiometer Mount & Test on Arrival - Mike W., Mike H. | |||
2. Program Underglow - Justin B.<br> | |||
3. Autonomous Code for tower blocking - Done and Checked In, Awaiting Testing<br> | |||
3.5. Swap autonomous up/down buttons - Jeff D. | |||
4. Manual Mode Lifter Code work - Calvin D.<br> | |||
5. Fix Welds on lifter - Mike W.<br> | |||
6. Make Second Lifter Structure - Amy Averill, Tom K. | |||
7. Order spare Electrical parts (Omron sensors, Multimeter, Current Meter) - Dave S., Mike H. | |||
8. Order spare gas shock and any other "hard to replace" mech parts - Tom K. | |||
9. Ensure we have spare drivetrain transmission - Tom C. |
Latest revision as of 15:37, 30 March 2010
List of Tasks & Leaders for Atlanta Preparations 2010
This is a list created to help us track the preparations for Atlanta. There is A LOT to be done, and we need everyone's help to do it. PLEASE pitch in and sign up for things if you haven't already.
General List
1. Unpack items from Boston - Jeff
2. Repack items for Atlanta - Jeff
3. Video Tape the Chairmans Presentation - Shauna/Becca/Kyle
4. Practice the Chairmans Presentation - Shauna/Becca/Kyle
5. Thunderbolts - Kim
6. Rookie Meet & Greet Booklet - Cynette
6a. Rookie Research - ??
7. Rookie Meet & Greet Planning - Cynette/Crystal/Lee
8. Press Releases - ??
9. Sponsor Newsletter - Matthieu/Val Drake
10. Sponsor Email - Val Drake
11. Make More Buttons - Mrs. Wolf and all others welcome.
12. Collect Boston Smugmug Photos - ??
13. Work on Scouting Laptops - Matthieu
14. PRINT Pit Scouting & Match Prep Sheets - Kyle
15. Make Master Schedule - Kim
16. Coordinate Signups for Championship Conferences - ??
17. Update Robot Sheet - Kim
18. New Chairmans Packets - Leann
19. Prep for Atlanta PR presentation - Lee Drake/Crystal
Robot List
1. Fix Potentiometer Mount & Test on Arrival - Mike W., Mike H.
2. Program Underglow - Justin B.
3. Autonomous Code for tower blocking - Done and Checked In, Awaiting Testing
3.5. Swap autonomous up/down buttons - Jeff D.
4. Manual Mode Lifter Code work - Calvin D.
5. Fix Welds on lifter - Mike W.
6. Make Second Lifter Structure - Amy Averill, Tom K.
7. Order spare Electrical parts (Omron sensors, Multimeter, Current Meter) - Dave S., Mike H.
8. Order spare gas shock and any other "hard to replace" mech parts - Tom K.
9. Ensure we have spare drivetrain transmission - Tom C.