Attendance

Start time:  6:30

End time:  9:30

Members present:  Vaughn T., Alex R., Dave B., Dean S.

Members Attending Next Meeting:

Tasks Completed

  • Integrated mock board with the drivetrain
  • Mocked up mounting board lamination
  • Discussed sensor integration with mechanical (see main electrical page)

Tasks In Progress

  • Encoder Termination

Tasks to Complete

  • task
    • sub-task
    • sub-task
  • task

Materials Needed

See Shopping List