2011:Electrical Main 1.25: Difference between revisions
From 1511Wookiee
Jump to navigationJump to search
No edit summary |
No edit summary |
||
(2 intermediate revisions by the same user not shown) | |||
Line 15: | Line 15: | ||
*Discussed sensor integration with mechanical (see main electrical page) | *Discussed sensor integration with mechanical (see main electrical page) | ||
= Tasks In Progress = | = Tasks In Progress = | ||
* | *Encoder Termination | ||
= Tasks to Complete = | = Tasks to Complete = | ||
See main electrical page | |||
= Materials Needed = | = Materials Needed = | ||
See Shopping List | |||
Latest revision as of 19:26, 25 January 2011
Attendance
Start time: 6:30
End time: 9:30
Members present: Vaughn T., Alex R., Dave B., Dean S.
Members Attending Next Meeting:
Tasks Completed
- Integrated mock board with the drivetrain
- Mocked up mounting board lamination
- Discussed sensor integration with mechanical (see main electrical page)
Tasks In Progress
- Encoder Termination
Tasks to Complete
See main electrical page
Materials Needed
See Shopping List