= Attendance = | = Attendance = | ||
'''Start time: 10:30''' | '''Start time: 10:30''' | ||
'''End time:''' | '''End time:''' 6:00 | ||
'''Members present: Matthieu D, Christian S, Manuel S., Vaughn, Dave B, Dave S''' | '''Members present: Matthieu D, Christian S, Manuel S., Vaughn, Dave B, Dave S''' | ||
'''Members Attending Next Meeting:''' | '''Members Attending Next Meeting:''' | ||
Line 11: | Line 11: | ||
= Tasks Completed = | = Tasks Completed = | ||
*Signal Light completely built, wired and tested - ready for mounting on robot | *Signal Light completely built, wired and tested - ready for mounting on robot | ||
*inventoried wire for the robot - we have the gauges and colors we need | *inventoried wire for the robot - we have the gauges and colors we need | ||
*Dave B further organized electrical parts - we got some more plastic bins | *Dave B further organized electrical parts - we got some more plastic bins to aid this | ||
= Tasks In Progress = | = Tasks In Progress = | ||
*Figure out cable routing | *Figure out cable routing | ||
**we believe we have a plan for routing wires around arm hinge out near the | **we believe we have a plan for routing wires around arm hinge out near the manipulator - take them around the side. | ||
** still need a plan for routing wires up into the arm at the main pivot point. | **still need a plan for routing wires up into the arm at the main pivot point. | ||
*task | *task | ||
= Tasks to Complete = | = Tasks to Complete = | ||
* | *mount main electrical board on robot and assemble/wire | ||
* | *need to cut to size the side electrical board | ||
= Materials Needed = | = Materials Needed = |
Latest revision as of 05:00, 7 February 2011
Attendance
Start time: 10:30
End time: 6:00
Members present: Matthieu D, Christian S, Manuel S., Vaughn, Dave B, Dave S
Members Attending Next Meeting:
Tasks Completed
- Signal Light completely built, wired and tested - ready for mounting on robot
- inventoried wire for the robot - we have the gauges and colors we need
- Dave B further organized electrical parts - we got some more plastic bins to aid this
Tasks In Progress
- Figure out cable routing
- we believe we have a plan for routing wires around arm hinge out near the manipulator - take them around the side.
- still need a plan for routing wires up into the arm at the main pivot point.
- task
Tasks to Complete
- mount main electrical board on robot and assemble/wire
- need to cut to size the side electrical board
Materials Needed
- task
- sub-task
- sub-task
- task