2011:Field 2/15/2011: Difference between revisions
Leadership (talk | contribs) No edit summary |
Leadership (talk | contribs) No edit summary |
||
(One intermediate revision by the same user not shown) | |||
Line 1: | Line 1: | ||
Members present: | Members present: Shayna, Jason, Amy | ||
<br>Members Attending Next Meeting: | <br>Members Attending Next Meeting: | ||
Line 11: | Line 11: | ||
Tasks Completed: | Tasks Completed: | ||
Task 1 - | Task 1 - Glued reflective tape to the upright poles | ||
Task 2 - | Task 2 - Mounted one set of cords for Rally field | ||
Task 3 - Made list of items that need to be completed this weekend prior to rally set-up | |||
<br> | <br> | ||
Line 21: | Line 23: | ||
<br>Tasks In Progress: | <br>Tasks In Progress: | ||
Task 1 - | Task 1 - Mounting second set of power cords | ||
Task 2 - | Task 2 - Finsih building final shelf in the closet | ||
<br> | <br> | ||
Line 33: | Line 35: | ||
Tasks to Complete: | Tasks to Complete: | ||
Task 1 - | Task 1 - Drill holes for rail alignment | ||
Task 2 - Mount post toppers | |||
Task 3 - Determine/Construct method to keep lane dividers in place (on order) | |||
Task 4 - Mounting system on player stations for power/connectivity (1 remaining to make) | |||
Task 5 - Drill holes in each player station for cords | |||
Task 6 - Drill 1 hole in each piece of Lexan for securing<br> | |||
Task 7 - Sensor platefor top of post<br> | |||
Task 8 - Plate to connect rails to alliance walls (on order from Harris) | |||
<br> | <br> | ||
Line 47: | Line 62: | ||
Materials Needed:<br>Item 1 - | Materials Needed:<br>Item 1 - | ||
Item 2 - | Item 2 - Remaing bolts that were the wrong size | ||
<br> | <br> |
Latest revision as of 06:48, 16 February 2011
Members present: Shayna, Jason, Amy
Members Attending Next Meeting:
Tasks Completed:
Task 1 - Glued reflective tape to the upright poles
Task 2 - Mounted one set of cords for Rally field
Task 3 - Made list of items that need to be completed this weekend prior to rally set-up
Tasks In Progress:
Task 1 - Mounting second set of power cords
Task 2 - Finsih building final shelf in the closet
Tasks to Complete:
Task 1 - Drill holes for rail alignment
Task 2 - Mount post toppers
Task 3 - Determine/Construct method to keep lane dividers in place (on order)
Task 4 - Mounting system on player stations for power/connectivity (1 remaining to make)
Task 5 - Drill holes in each player station for cords
Task 6 - Drill 1 hole in each piece of Lexan for securing
Task 7 - Sensor platefor top of post
Task 8 - Plate to connect rails to alliance walls (on order from Harris)
Materials Needed:
Item 1 -
Item 2 - Remaing bolts that were the wrong size
Images & Additional Updates:
(Make sure you are in the Rich Editor and use the upload file button on the toolbox to the left to upload the file, then insert an image using the button above. Sizing can be done using the length/width pixel size)