Line 21: | Line 21: | ||
Before FLR | Before FLR | ||
1 Order | 1 Order spare parts from Harris | ||
2 | 2 Redesign manipulator wheel shafts for maintainability | ||
3 | 3 Design chain guard | ||
4 | 4 Design manipulator wheel guard | ||
5 | 5 Design minibot roof and backstop | ||
<br> | |||
Complete; | |||
1 Order McmasterCarr parts <br> | |||
= Materials Needed = | = Materials Needed = |
Revision as of 09:13, 26 February 2011
Attendance
Start time:
End time:
Members present:
Members Attending Next Meeting:
Tasks to Complete
At FLR
1 Put bolts in the corners of the upper structure
2 Put on chain guard
3 Put on minibot roof
Before FLR
1 Order spare parts from Harris
2 Redesign manipulator wheel shafts for maintainability
3 Design chain guard
4 Design manipulator wheel guard
5 Design minibot roof and backstop
Complete;
1 Order McmasterCarr parts
Materials Needed
- task
- sub-task
- sub-task
- task