= Attendance = | = Attendance = | ||
'''Start time:''' | '''Start time:''' 10 am | ||
'''End time:''' | '''End time:''' 9 pm | ||
'''Members present:''' | '''Members present:''' Alex Wolf, Mr. Wolf, Josh, Brianna Mancine | ||
'''Members Attending Next Meeting:''' | '''Members Attending Next Meeting:''' | ||
Line 11: | Line 11: | ||
= Tasks Completed = | = Tasks Completed = | ||
* | *here's the robot so far! | ||
** | |||
** | [[File:jan 27 2013.jpg]] | ||
* | |||
*DONE- check 54 inch cyl | |||
*DONE Alex- Design Black arm pivot | |||
*DONE Alex- Put in battery | |||
*DONE Alex -Add lightening holes all over the place | |||
*Done- Revise part #002 with "far side" note | |||
*Done- Redesign 002 elevator C chanel to accomodate "new" pyramid. | |||
*SENT OUT A LOT OF PARTS | |||
= Tasks In Progress = | = Tasks In Progress = | ||
* | *Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2. | ||
** | **put in shopping list | ||
= Tasks to Complete = | = Tasks to Complete = | ||
Line 66: | Line 73: | ||
= Materials Needed = | = Materials Needed = | ||
* | *see google list | ||
Revision as of 18:07, 27 January 2013
Attendance
Start time: 10 am
End time: 9 pm
Members present: Alex Wolf, Mr. Wolf, Josh, Brianna Mancine
Members Attending Next Meeting:
Tasks Completed
- here's the robot so far!
- DONE- check 54 inch cyl
- DONE Alex- Design Black arm pivot
- DONE Alex- Put in battery
- DONE Alex -Add lightening holes all over the place
- Done- Revise part #002 with "far side" note
- Done- Redesign 002 elevator C chanel to accomodate "new" pyramid.
- SENT OUT A LOT OF PARTS
Tasks In Progress
- Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.
- put in shopping list
Tasks to Complete
Release all fab parts 1/24/13
list and order all assembly hardware
DONE- check 54 inch cyl
DONE Alex- Design Black arm pivot
DONE Alex- Put in battery
Design release mechanism for red arms and black arms
Alex- Design restraining mechanism for red arms and black arms
Brianna- Add sensors to model
Brianna- Design the cross member with leg guide for Red arms and Black arms
DONE Alex -Add lightening holes all over the place
Order all purchase parts
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
Use cross members to strengthen the elevator shafts
Belay attachment points
Done- Revise part #002 with "far side" note
Done- Redesign 002 elevator C chanel to accomodate "new" pyramid.
Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.
ON HOLD - transmission chain tentioner
Materials Needed
- see google list