2013:Climber 01.27: Difference between revisions
No edit summary |
Mechanical1 (talk | contribs) No edit summary |
||
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
= Attendance = | = Attendance = | ||
'''Start time: ''' | '''Start time:''' 10 am | ||
'''End time: ''' | '''End time:''' 8:30 pm | ||
'''Members present: ''' | '''Members present:''' Alex Wolf, Mr. Wolf, Josh, Brianna Mancine | ||
'''Members Attending Next Meeting: ''' | '''Members Attending Next Meeting:''' | ||
= Tasks Completed = | = Tasks Completed = | ||
* | *here's the robot so far! | ||
** | |||
** | [[File:jan 27 2013.jpg]] | ||
* | |||
*DONE- check 54 inch cyl | |||
*DONE Alex- Design Black arm pivot | |||
*DONE Alex- Put in battery | |||
*DONE Alex -Add lightening holes all over the place | |||
*Done- Revise part #002 with "far side" note | |||
*Done- Redesign 002 elevator C chanel to accomodate "new" pyramid. | |||
*SENT OUT A LOT OF PARTS | |||
= Tasks In Progress = | |||
* | |||
** | *Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2. | ||
**put in shopping list | |||
= Tasks to Complete = | = Tasks to Complete = | ||
* | * | ||
Release all fab parts 1/24/13 | |||
list and order all assembly hardware | |||
DONE- check 54 inch cyl | |||
DONE Alex- Design Black arm pivot | |||
DONE Alex- Put in battery | |||
Design release mechanism for red arms and black arms | |||
Alex- Design restraining mechanism for red arms and black arms | |||
Brianna- Add sensors to model | |||
Brianna- Design the cross member with leg guide for Red arms and Black arms | |||
DONE Alex -Add lightening holes all over the place | |||
Order all purchase parts | |||
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline | |||
Use cross members to strengthen the elevator shafts | |||
Belay attachment points | |||
Done- Revise part #002 with "far side" note | |||
Done- Redesign 002 elevator C chanel to accomodate "new" pyramid. | |||
Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2. | |||
ON HOLD - transmission chain tentioner | |||
= Materials Needed = | = Materials Needed = | ||
* | *see google list | ||
Latest revision as of 18:10, 27 January 2013
Attendance
Start time: 10 am
End time: 8:30 pm
Members present: Alex Wolf, Mr. Wolf, Josh, Brianna Mancine
Members Attending Next Meeting:
Tasks Completed
- here's the robot so far!
- DONE- check 54 inch cyl
- DONE Alex- Design Black arm pivot
- DONE Alex- Put in battery
- DONE Alex -Add lightening holes all over the place
- Done- Revise part #002 with "far side" note
- Done- Redesign 002 elevator C chanel to accomodate "new" pyramid.
- SENT OUT A LOT OF PARTS
Tasks In Progress
- Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.
- put in shopping list
Tasks to Complete
Release all fab parts 1/24/13
list and order all assembly hardware
DONE- check 54 inch cyl
DONE Alex- Design Black arm pivot
DONE Alex- Put in battery
Design release mechanism for red arms and black arms
Alex- Design restraining mechanism for red arms and black arms
Brianna- Add sensors to model
Brianna- Design the cross member with leg guide for Red arms and Black arms
DONE Alex -Add lightening holes all over the place
Order all purchase parts
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
Use cross members to strengthen the elevator shafts
Belay attachment points
Done- Revise part #002 with "far side" note
Done- Redesign 002 elevator C chanel to accomodate "new" pyramid.
Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.
ON HOLD - transmission chain tentioner
Materials Needed
- see google list