Attendance
Start time: 6:30
End time: 9:30
Members present: Vaughn T., Alex R., Dave B., Dean S.
Members Attending Next Meeting:
Tasks Completed
- Integrated mock board with the drivetrain
- Mocked up mounting board lamination
- Discussed sensor integration with mechanical (see main electrical page)
Tasks In Progress
- Encoder Termination
Tasks to Complete
See main electrical page
Materials Needed
See Shopping List