2013:Electrical Controls 01.24: Difference between revisions

From 1511Wookiee
Jump to navigationJump to search
No edit summary
 
No edit summary
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
= Attendance =
= Attendance =


'''Start time: '''
'''Start time: 5:00 pm'''
 
'''End time: '''
 
'''Members present: '''


'''Members Attending Next Meeting: '''
'''End time: 9:00 pm'''


= Tasks Completed =
'''Members present: Shayna R., Ben S., Nick B., Gafei S., Matt B., Kyle'''


*task
'''Members Attending Next Meeting: Shayna R., Ben S., Nick B., Gafei S., Matt B., Kyle'''
**sub-task
**sub-task
*task


= Tasks In Progress =  
= Tasks In Progress =


*task
*Listing Sensors to be used on climber mechanism.
**sub-task
*Finish sketch/design in inventor.
**sub-task
*task


= Tasks to Complete =
= Tasks to Complete =


*task
*Complete list of sensors
**sub-task
*Listing any other materials needed
**sub-task
*Complete all Inventor Drawings
*task
*Select an extra set of hinges.


= Materials Needed =
= Materials Needed =


*task
*Refer to the BOM
**sub-task
**sub-task
*task

Latest revision as of 19:00, 24 January 2013

Attendance

Start time: 5:00 pm

End time: 9:00 pm

Members present: Shayna R., Ben S., Nick B., Gafei S., Matt B., Kyle

Members Attending Next Meeting: Shayna R., Ben S., Nick B., Gafei S., Matt B., Kyle

Tasks In Progress

  • Listing Sensors to be used on climber mechanism.
  • Finish sketch/design in inventor.

Tasks to Complete

  • Complete list of sensors
  • Listing any other materials needed
  • Complete all Inventor Drawings
  • Select an extra set of hinges.

Materials Needed

  • Refer to the BOM