2013:Climber 01.26: Difference between revisions

From 1511Wookiee
Jump to navigationJump to search
No edit summary
 
No edit summary
 
(11 intermediate revisions by the same user not shown)
Line 1: Line 1:
= Attendance =
= Attendance =


'''Start time: '''
'''Start time:'''


'''End time: '''
'''End time:'''


'''Members present: '''
'''Members present:'''


'''Members Attending Next Meeting: '''
'''Members Attending Next Meeting:'''


= Tasks Completed =
= Tasks Completed =
Line 17: Line 16:
*task
*task


= Tasks In Progress =  
= Tasks In Progress =


*task
*task
Line 26: Line 25:
= Tasks to Complete =
= Tasks to Complete =


*task
Release all fab parts 1/24/13
**sub-task
 
**sub-task
list and order all assembly hardware
*task
 
DONE-   check 54 inch cyl
 
DONE Alex-   Design Black arm pivot
 
DONE Alex-   Put in battery
 
Design release mechanism for red arms and black arms
 
Design restraining mechanism for red arms and black arms
 
Brianna-   Add sensors to model
 
Brianna-   Design the cross member with leg guide for Red arms and Black arms
 
DONE Alex -Add lightening holes all over the place
 
Order all purchase parts
 
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
 
Use cross members to strengthen the elevator shafts
 
Belay attachment points
 
Revise part #002 with "far side" note
 
Redesign 002 elevator C chanel to accomodate "new" pyramid.
 
          Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.
 
ON HOLD - transmission chain tentioner
 
 
 
 


= Materials Needed =
= Materials Needed =

Latest revision as of 13:07, 27 January 2013

Attendance

Start time:

End time:

Members present:

Members Attending Next Meeting:

Tasks Completed

  • task
    • sub-task
    • sub-task
  • task

Tasks In Progress

  • task
    • sub-task
    • sub-task
  • task

Tasks to Complete

Release all fab parts 1/24/13

list and order all assembly hardware

DONE-   check 54 inch cyl

DONE Alex-   Design Black arm pivot

DONE Alex-   Put in battery

Design release mechanism for red arms and black arms

Design restraining mechanism for red arms and black arms

Brianna-   Add sensors to model

Brianna-   Design the cross member with leg guide for Red arms and Black arms

DONE Alex -Add lightening holes all over the place

Order all purchase parts

Combine all subteams parts and design the CG to be within +/- one inch from bot centerline

Use cross members to strengthen the elevator shafts

Belay attachment points

Revise part #002 with "far side" note

Redesign 002 elevator C chanel to accomodate "new" pyramid.

          Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.

ON HOLD - transmission chain tentioner

 

 

Materials Needed

  • task
    • sub-task
    • sub-task
  • task