= Tasks to Complete =
= Tasks to Complete =


*
Release all fab parts 1/24/13


Release all fab parts 1/24/13
list and order all assembly hardware


Design stationary arm pivot
DONE-   check 54 inch cyl


Put in battery
DONE Alex-   Design Black arm pivot


Add tensioners
DONE Alex-   Put in battery


Design release mechanism for long arms and short arms
Design release mechanism for red arms and black arms


Design restraining mechanism for long arms and short arms
Design restraining mechanism for red arms and black arms


Add sensors to model
Brianna-   Add sensors to model


Design the cross member with leg guide for long arms and short arms
Brianna-   Design the cross member with leg guide for Red arms and Black arms


Add lightening holes all over the place
DONE Alex -Add lightening holes all over the place


Order all purchase parts
Order all purchase parts


Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
Move upper arms to back of boom


Use cross members to strengthen the elevator shafts
Use cross members to strengthen the elevator shafts


Belay attachment points
Belay attachment points
Revise part #002 with "far side" note
Redesign 002 elevator C chanel to accomodate "new" pyramid.
          Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.


ON HOLD - transmission chain tentioner
ON HOLD - transmission chain tentioner


 
 
*


 
 

Latest revision as of 13:07, 27 January 2013

Attendance

Start time:

End time:

Members present:

Members Attending Next Meeting:

Tasks Completed

  • task
    • sub-task
    • sub-task
  • task

Tasks In Progress

  • task
    • sub-task
    • sub-task
  • task

Tasks to Complete

Release all fab parts 1/24/13

list and order all assembly hardware

DONE-   check 54 inch cyl

DONE Alex-   Design Black arm pivot

DONE Alex-   Put in battery

Design release mechanism for red arms and black arms

Design restraining mechanism for red arms and black arms

Brianna-   Add sensors to model

Brianna-   Design the cross member with leg guide for Red arms and Black arms

DONE Alex -Add lightening holes all over the place

Order all purchase parts

Combine all subteams parts and design the CG to be within +/- one inch from bot centerline

Use cross members to strengthen the elevator shafts

Belay attachment points

Revise part #002 with "far side" note

Redesign 002 elevator C chanel to accomodate "new" pyramid.

          Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.

ON HOLD - transmission chain tentioner

 

 

Materials Needed

  • task
    • sub-task
    • sub-task
  • task