Progress and Completion:  
Progress and Completion:  


*Finished the mouse wire layout.<br>
*Finished the mouse wire layout.
*Filed the mouse, still needs a little bit of work.<br>


<br>  
<br>  
Line 34: Line 35:
*Rofl(Waffle)-Bot needs to be fixed  
*Rofl(Waffle)-Bot needs to be fixed  
*design a cover for the back of the control box  
*design a cover for the back of the control box  
*PUT MOUSE BALL BACK IN!!!
*PUT MOUSE BALL BACK IN!!!  
*Mechanical gets to fix the mouse.

Revision as of 16:23, 22 October 2009

Attendance: Mike H, Tom P, Vaughn, Crystal V, Matthieu D, Andy M, Dave and Dave, Jeff.


Goals of the night:

  • Finish the Mouse repairs
  • fix the moue wire labels.


Mouse wire layout:

XA=AD2

XB=BD2

YA=AD1

YB=BD1


Progress and Completion:

  • Finished the mouse wire layout.
  • Filed the mouse, still needs a little bit of work.



Next week's meeting:

  • Rofl(Waffle)-Bot needs to be fixed
  • design a cover for the back of the control box
  • PUT MOUSE BALL BACK IN!!!
  • Mechanical gets to fix the mouse.