2009:Mechanical 1 - 1.10.09: Difference between revisions
From 1511Wookiee
Jump to navigationJump to search
Mechanical1 (talk | contribs) (New page: '''1.10.2009''' '''Start time:''' 10:00pm '''End time:''' 8:00pm '''Members present: '''[Josh Goodman, Alex Wolf, Alex Vadas, Mike Montemallo] - [Mike Wolf, Dave Vadas] <br>'''Tasks co...) |
Mechanical1 (talk | contribs) No edit summary |
||
Line 1: | Line 1: | ||
'''1.10.2009''' | '''1.10.2009''' | ||
'''Start time:''' 10:00pm | '''Start time:''' 10:00pm | ||
'''End time:''' 8:00pm | '''End time:''' 8:00pm | ||
'''Members present: '''[Josh Goodman, Alex Wolf, Alex Vadas, Mike Montemallo] - [Mike Wolf, Dave Vadas] | '''Members present: '''[Josh Goodman, Alex Wolf, Alex Vadas, Mike Montemallo] - [Mike Wolf, Dave Vadas] | ||
<br>'''Tasks completed:''' | <br>'''Tasks completed:''' | ||
- Started to prototype conveyor system<br> | - Started to prototype conveyor system<br> | ||
- | - Looked at weaknesses of conveyor and gatherer systems.<br> | ||
<br>Tasks to complete: | <br>'''Tasks to complete:'''<br>-Making appropriate adjustments to prototype<br> | ||
-Making components for Mech 2 in inventor<br> | |||
-<br> |
Revision as of 09:40, 11 January 2009
1.10.2009
Start time: 10:00pm
End time: 8:00pm
Members present: [Josh Goodman, Alex Wolf, Alex Vadas, Mike Montemallo] - [Mike Wolf, Dave Vadas]
Tasks completed:
- Started to prototype conveyor system
- Looked at weaknesses of conveyor and gatherer systems.
Tasks to complete:
-Making appropriate adjustments to prototype
-Making components for Mech 2 in inventor