* | *repaired RS-232/CAN cable on mock board and installed D-connector shell. | ||
*anylize material [[Stress]] capability<br> | |||
*anylize material [[ | |||
= Tasks In Progress = | = Tasks In Progress = |
Revision as of 06:39, 27 January 2011
Attendance
Start time: 6:00
End time: 9:00
Members present: Vaughn, Alex R., Dean S., Dave S., Cristian S.
Members Attending Next Meeting:
Tasks Completed
- repaired RS-232/CAN cable on mock board and installed D-connector shell.
- anylize material Stress capability
Tasks In Progress
- task
- sub-task
- sub-task
- task
Tasks to Complete
- task
- sub-task
- sub-task
- task
Materials Needed
- task
- sub-task
- sub-task