Line 11: Line 11:
= Tasks Completed  =
= Tasks Completed  =


*task
Arm Shaft Machining
**sub-task
**sub-task
*task


= Tasks In Progress =
Drawing completed (Alex W) <span id="fck_dom_range_temp_1297715372402_477" />
 
* Fabricate Arm/Sprocket Mounting Angles
 
* Arm Hinge Shaft machining
 
Drawings complete (TDK)
 
* Buy or find E-Rings *
 
* Layout and Drill Arm Extensions
 
Partially complete (Jonathan, Manuel)<br>* Assemble Latches and Springs<br>Partially complete (Manuel)
 
* Machine chamfer into Big Sprocket (Tony D)IN-PROCESS<br>* Mill Arm Slots
 
In-process (Alex W)<br>* Deburr Arm Holes
 
Completed (Lizzy)<br>* Drill and Tap AndyMark Hub for Arm<br>Drawing Required<br>* Assemble AndyMark Hub to Arm <br>
 
<br>'''Tasks In Progress'''
 
Find or make plastic spacers<br>* Buy #8 button head screws *<br>* Bore lightening holes in 66T sprocket ON HOLD<br>Need drawing
 
 
 
 
 
 
 
 
 
 
 
<br>Materials Needed


*Arm Shaft Machining IN-PROCESS<br>Drawing completed (Alex W) COMPLETED<br>* Fabricate Arm/Sprocket Mounting Angles COMPLETED<br>* Arm Hinge Shaft machining COMPLETED<br>Drawings complete (TDK) COMPLETED<br>* Buy or find E-Rings * PENDING<br>* Layout and Drill Arm Extensions COMPLETED<br>Partially complete (Jonathan, Manuel)<br>* Assemble Latches and Springs<br>Partially complete (Manuel)<br>Find or make plastic spacers<br>* Buy #8 button head screws *<br>* Machine chamfer into Big Sprocket (Tony D)IN-PROCESS<br>* Bore lightening holes in 66T sprocket ON HOLD<br>Need drawing<br>* Mill Arm Slots COMPLETED<br>In-process (Alex W)<br>* Deburr Arm Holes COMPLETED<br>Completed (Lizzy)<br>* Drill and Tap AndyMark Hub for Arm<br>Drawing Required<br>* Assemble AndyMark Hub to Arm <br>Materials Needed
*task  
*task  
**sub-task  
**sub-task  
**sub-task
**sub-task
*task
*task

Revision as of 13:30, 14 February 2011

Attendance

Start time:

End time:

Members present:

Members Attending Next Meeting:

Tasks Completed

Arm Shaft Machining

Drawing completed (Alex W)

  • Fabricate Arm/Sprocket Mounting Angles
  • Arm Hinge Shaft machining

Drawings complete (TDK)

  • Buy or find E-Rings *
  • Layout and Drill Arm Extensions

Partially complete (Jonathan, Manuel)
* Assemble Latches and Springs
Partially complete (Manuel)

  • Machine chamfer into Big Sprocket (Tony D)IN-PROCESS
    * Mill Arm Slots

In-process (Alex W)
* Deburr Arm Holes

Completed (Lizzy)
* Drill and Tap AndyMark Hub for Arm
Drawing Required
* Assemble AndyMark Hub to Arm


Tasks In Progress

Find or make plastic spacers
* Buy #8 button head screws *
* Bore lightening holes in 66T sprocket ON HOLD
Need drawing







Materials Needed

  • task
    • sub-task
    • sub-task
  • task