This list is to track Robot/Controls activities that will be performed at FLR once the robot is uncrated and the pit crew can start working on the robot.
| Task | Team | Priority | Estimated Time |
| Mount and connect second turret sensor | Electrical | 2 | 15m |
| Install conveyor chain tensioner | Mech | 6 | 20m |
| Replace beater bar resetting breaker with 20A fuse | Electrical | 4 | <5m |
| Clean up wire from old flag sensors | Electrical | 7 | 10m |
| Turret Encoder - make it work | Elec/Mech/Prog | 1 | 45m |
| Realign Wing Potentiometer | Elec/Prog | 5 | 15m |
| Phase B of Turrret to Side Car - Remove Drive Encoders | Elec/Prog | 3 | 15m |
| Initial Sensor Ring Out | Elec/Mech/Prog | 8 | 30m |