= Attendance =
= Attendance =


'''Start time: '''
'''Start time:'''


'''End time: '''
'''End time:'''


'''Members present: '''
'''Members present:'''


'''Members Attending Next Meeting: '''
'''Members Attending Next Meeting:'''


= Tasks Completed =
= Tasks Completed =
Line 17: Line 16:
*task
*task


= Tasks In Progress =  
= Tasks In Progress =


*task
*task
Line 26: Line 25:
= Tasks to Complete =
= Tasks to Complete =


*task
*
**sub-task
Release all fab parts 1/24/13
**sub-task
 
*task
list and order all assembly hardware
 
DONE- check 54 inch cyl
 
DONE Alex- Design Black arm pivot
 
DONE Alex- Put in battery
 
Design release mechanism for red arms and black arms
 
Alex-   Design restraining mechanism for red arms and black arms
 
Brianna- Add sensors to model
 
Brianna- Design the cross member with leg guide for Red arms and Black arms
 
DONE Alex -Add lightening holes all over the place
 
Order all purchase parts
 
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
 
Use cross members to strengthen the elevator shafts
 
Belay attachment points
 
Done-  Revise part #002 with "far side" note
 
Done-  Redesign 002 elevator C chanel to accomodate "new" pyramid.
 
Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.
 
ON HOLD - transmission chain tentioner
 
 


= Materials Needed =
= Materials Needed =

Revision as of 14:03, 27 January 2013

Attendance

Start time:

End time:

Members present:

Members Attending Next Meeting:

Tasks Completed

  • task
    • sub-task
    • sub-task
  • task

Tasks In Progress

  • task
    • sub-task
    • sub-task
  • task

Tasks to Complete

Release all fab parts 1/24/13

list and order all assembly hardware

DONE- check 54 inch cyl

DONE Alex- Design Black arm pivot

DONE Alex- Put in battery

Design release mechanism for red arms and black arms

Alex-   Design restraining mechanism for red arms and black arms

Brianna- Add sensors to model

Brianna- Design the cross member with leg guide for Red arms and Black arms

DONE Alex -Add lightening holes all over the place

Order all purchase parts

Combine all subteams parts and design the CG to be within +/- one inch from bot centerline

Use cross members to strengthen the elevator shafts

Belay attachment points

Done-  Revise part #002 with "far side" note

Done-  Redesign 002 elevator C chanel to accomodate "new" pyramid.

Now we don't have enough c chanel stock at Chamtek and will have to order 2 and more stock for 2 more for bot 2.

ON HOLD - transmission chain tentioner


Materials Needed

  • task
    • sub-task
    • sub-task
  • task