2013:Climber 01.29: Difference between revisions
From 1511Wookiee
Jump to navigationJump to search
No edit summary |
Mechanical1 (talk | contribs) No edit summary |
||
Line 1: | Line 1: | ||
= Attendance = | = Attendance = | ||
'''Start time: ''' | '''Start time:''' | ||
'''End time: ''' | '''End time:''' | ||
'''Members present: ''' | '''Members present:''' | ||
'''Members Attending Next Meeting: ''' | '''Members Attending Next Meeting:''' | ||
= Tasks Completed = | = Tasks Completed = | ||
Line 17: | Line 16: | ||
*task | *task | ||
= Tasks In Progress = | = Tasks In Progress = | ||
*task | *task | ||
Line 24: | Line 23: | ||
*task | *task | ||
= Tasks to Complete = | = Tasks to Complete list and order all assembly hardware = | ||
* | |||
list and order all assembly hardware | |||
Design release mechanism for red arms and black arms | |||
Alex- Design restraining mechanism for red arms and black arms | |||
Brianna- Add sensors to model | |||
Brianna- Design the cross member with leg guide for Red arms and Black arms | |||
Order all purchase parts | |||
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline | |||
Use cross members to strengthen the elevator shafts | |||
Belay attachment points | |||
Now we don't have enough c chanel stock at Chamtek and will have to order 2 parts and more stock for 2 more for bot 2. | |||
= Materials Needed = | = Materials Needed = |
Latest revision as of 17:50, 27 January 2013
Attendance
Start time:
End time:
Members present:
Members Attending Next Meeting:
Tasks Completed
- task
- sub-task
- sub-task
- task
Tasks In Progress
- task
- sub-task
- sub-task
- task
Tasks to Complete list and order all assembly hardware
list and order all assembly hardware
Design release mechanism for red arms and black arms
Alex- Design restraining mechanism for red arms and black arms
Brianna- Add sensors to model
Brianna- Design the cross member with leg guide for Red arms and Black arms
Order all purchase parts
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
Use cross members to strengthen the elevator shafts
Belay attachment points
Now we don't have enough c chanel stock at Chamtek and will have to order 2 parts and more stock for 2 more for bot 2.
Materials Needed
- task
- sub-task
- sub-task
- task