2010:Drivetrain: Difference between revisions

From 1511Wookiee
Jump to navigationJump to search
(gannon update to master task list)
(added week 5 pages)
Line 3: Line 3:
1. Complete Bill of Materials (Need to post BOM, should be complete -JSG 2/02)<br>
1. Complete Bill of Materials (Need to post BOM, should be complete -JSG 2/02)<br>


2. <strike>Fix Rubbing Issue on Mock Drivetrain </strike>  
2. <strike>Fix Rubbing Issue on Mock Drivetrain</strike>


3. Make Bumpers (partially complete. May need fabric? -JSG 2/02)<br>
3. Make Bumpers (partially complete. May need fabric? -JSG 2/02)<br>


4.<strike>Reassemble Drivetrain when parts return from Powdercoating</strike>
4.<strike>Reassemble Drivetrain when parts return from Powdercoating</strike>  


5. Design Mouse Sensor Mount (in progress parts to be ordered by 2/04 -JSG 2/02)<br>
5. Design Mouse Sensor Mount (in progress parts to be ordered by 2/04 -JSG 2/02)<br>
Line 37: Line 37:
[[Drivetrain 1.18.2009|Drivetrain 1.18.2009]]  
[[Drivetrain 1.18.2009|Drivetrain 1.18.2009]]  


'''Week 3 - '''''<b>28 Days Left!!</b>''<br>  
'''Week 3 - '''''<b>28 Days Left!!</b>''<br>


[[Drivetrain 1.20.2009|Drivetrain 1.20.2009]]  
[[Drivetrain 1.20.2009|Drivetrain 1.20.2009]]  
Line 51: Line 51:
'''Week 4 - '''''<b>21 Days Left!!</b>''  
'''Week 4 - '''''<b>21 Days Left!!</b>''  


[[Drivetrain 1.27.2009|Drivetrain 1.27.2009]]<br>  
[[Drivetrain 1.27.2009|Drivetrain 1.27.2009]]<br>


[[Drivetrain 1.28.2009|Drivetrain 1.28.2009]]  
[[Drivetrain 1.28.2009|Drivetrain 1.28.2009]]  
Line 60: Line 60:


[[Drivetrain 2.1.2009|Drivetrain 2.1.2009]]  
[[Drivetrain 2.1.2009|Drivetrain 2.1.2009]]  
'''Week 5 - '''''<span style="color: #ff0000">'''14 Days Left!!'''</span>''<span style="color: #ff0000" />
[[Drivetrain 2.3.2009|Drivetrain 2.3.2009]]
[[Drivetrain 2.4.2009|Drivetrain 2.4.2009]]
[[Drivetrain 2.5.2009|Drivetrain 2.5.2009]]
[[Drivetrain 2.7.2009|Drivetrain 2.7.2009]]
[[Drivetrain 2.8.2009|Drivetrain 2.8.2009]]


----
----


'''''Please Label All Notebook Pages&nbsp;<u>Drivetrain X.XX.2009</u> to avoid confusion'''''.
'''''Please Label All Notebook Pages&nbsp;<u>Drivetrain X.XX.2009</u> to avoid confusion'''''.

Revision as of 12:09, 4 February 2009

Drivetrain Master Task List

1. Complete Bill of Materials (Need to post BOM, should be complete -JSG 2/02)

2. Fix Rubbing Issue on Mock Drivetrain

3. Make Bumpers (partially complete. May need fabric? -JSG 2/02)

4.Reassemble Drivetrain when parts return from Powdercoating

5. Design Mouse Sensor Mount (in progress parts to be ordered by 2/04 -JSG 2/02)

Drivetrain Subteam's Engineering Notebook

Week 1 - 42 Days Left!!

Drivetrain 1.6.2009

Drivetrain 1.7.2009

Drivetrain 1.8.2009

Drivetrain 1.10.2009

Drivetrain 1.11.2009

Week 2 - 35 Days Left!!

Drivetrain 1.13.2009

Drivetrain 1.14.2009

Drivetrain 1.15.2009

Drivetrain 1.17.2009

Drivetrain 1.18.2009

Week 3 - 28 Days Left!!

Drivetrain 1.20.2009

Drivetrain 1.21.2009

Drivetrain 1.22.2009

Drivetrain 1.24.2009

Drivetrain 1.25.2009

Week 4 - 21 Days Left!!

Drivetrain 1.27.2009

Drivetrain 1.28.2009

Drivetrain 1.29.2009

Drivetrain 1.31.2009

Drivetrain 2.1.2009

Week 5 - 14 Days Left!!

Drivetrain 2.3.2009

Drivetrain 2.4.2009

Drivetrain 2.5.2009

Drivetrain 2.7.2009

Drivetrain 2.8.2009


Please Label All Notebook Pages Drivetrain X.XX.2009 to avoid confusion.