2011:Controls 2.3: Difference between revisions

From 1511Wookiee
Jump to navigationJump to search
No edit summary
No edit summary
Line 11: Line 11:
= Tasks Completed  =
= Tasks Completed  =


*The functional block diagram is completed in electrical form. It is listed below:<br>
*The functional block diagram is completed in electrical form. It is listed below:<br>[[Image:Control_wire_layout.jpg]]<br><br>  
**sub-task  
**sub-task  
**sub-task  
**sub-task  
Line 18: Line 18:
= Tasks In Progress  =
= Tasks In Progress  =


*task
*Schematics need to be draw up for formal wire layout of control undercarriage<br>
**sub-task
**Addition of potentiometers to paper stencil <br>
**sub-task
**Publish IO maps to wiki<br>
*task
*task


= Tasks to Complete  =
= Tasks to Complete  =


*task
*Figure out wiring for control system&nbsp;
**sub-task
**figure out additional switch functions<br>
**sub-task
**Figure out method to secure classmate computer<br>
*task
*Mount preset buttons onto board<br>


= Materials Needed  =
= Materials Needed  =


*task
*Need preset buttons&nbsp;
**sub-task
**sheet metal prototype
**sub-task  
**sub-task  
*task
*task

Revision as of 18:23, 3 February 2011

Attendance

Start time: 6PM

End time:

Members present: Crystal, JP, Quinten, Gafei

Members Attending Next Meeting:

Tasks Completed

  • The functional block diagram is completed in electrical form. It is listed below:
    Control wire layout.jpg

    • sub-task
    • sub-task
  • task

Tasks In Progress

  • Schematics need to be draw up for formal wire layout of control undercarriage
    • Addition of potentiometers to paper stencil
    • Publish IO maps to wiki
  • task

Tasks to Complete

  • Figure out wiring for control system 
    • figure out additional switch functions
    • Figure out method to secure classmate computer
  • Mount preset buttons onto board

Materials Needed

  • Need preset buttons 
    • sheet metal prototype
    • sub-task
  • task