2011:Mechanical 2 2.12: Difference between revisions

From 1511Wookiee
Jump to navigationJump to search
(New page: = Attendance = '''Start time: ''' '''End time: ''' '''Members present: ''' '''Members Attending Next Meeting: ''' = Tasks Completed = *task **sub-task **sub-task *task = Tasks In Pr...)
 
No edit summary
Line 23: Line 23:
*task
*task


= Tasks to Complete =
= Tasks to Complete =


*task
Arm Tasks
**sub-task
 
**sub-task
* Arm Shaft Machining '''IN-PROCESS'''<br> Drawing completed (Alex W) '''COMPLETED'''<br> * Fabricate Arm/Sprocket Mounting Angles '''COMPLETED'''<br> * Arm Hinge Shaft machining '''COMPLETED'''<br> Drawings complete (TDK) '''COMPLETED'''<br> * Buy or find E-Rings * '''PENDING'''<br> * Layout and Drill Arm Extensions '''COMPLETED'''<br> <strike>Partially complete (Jonathan, Manuel)</strike><br> * Assemble Latches and Springs<br> Partially complete (Manuel)<br> Find or make plastic spacers<br> * Buy #8 button head screws *<br> * Machine chamfer into Big Sprocket (Tony D)'''IN-PROCESS'''<br> * Bore lightening holes in 66T sprocket '''ON HOLD'''<br> <strike>Need drawing</strike><br> * Mill Arm Slots '''COMPLETED'''<br> <strike>In-process (Alex W)</strike><br> * Deburr Arm Holes '''COMPLETED'''<br> <strike>Completed (Lizzy)</strike><br> * Drill and Tap AndyMark Hub for Arm<br> Drawing Required<br> * Assemble AndyMark Hub to Arm
*task


= Materials Needed =
= Materials Needed =

Revision as of 09:14, 12 February 2011

Attendance

Start time:

End time:

Members present:

Members Attending Next Meeting:

Tasks Completed

  • task
    • sub-task
    • sub-task
  • task

Tasks In Progress

  • task
    • sub-task
    • sub-task
  • task

Tasks to Complete

Arm Tasks

  • Arm Shaft Machining IN-PROCESS
    Drawing completed (Alex W) COMPLETED
    * Fabricate Arm/Sprocket Mounting Angles COMPLETED
    * Arm Hinge Shaft machining COMPLETED
    Drawings complete (TDK) COMPLETED
    * Buy or find E-Rings * PENDING
    * Layout and Drill Arm Extensions COMPLETED
    Partially complete (Jonathan, Manuel)
    * Assemble Latches and Springs
    Partially complete (Manuel)
    Find or make plastic spacers
    * Buy #8 button head screws *
    * Machine chamfer into Big Sprocket (Tony D)IN-PROCESS
    * Bore lightening holes in 66T sprocket ON HOLD
    Need drawing
    * Mill Arm Slots COMPLETED
    In-process (Alex W)
    * Deburr Arm Holes COMPLETED
    Completed (Lizzy)
    * Drill and Tap AndyMark Hub for Arm
    Drawing Required
    * Assemble AndyMark Hub to Arm

Materials Needed

  • task
    • sub-task
    • sub-task
  • task