2013:Electrical Controls 01.26: Difference between revisions
From 1511Wookiee
Jump to navigationJump to search
No edit summary |
No edit summary |
||
Line 11: | Line 11: | ||
= Tasks In Progress = | = Tasks In Progress = | ||
* | *Define functionality on control functions. | ||
* | *Verify current model dimensions. | ||
*Design dimensions for strap buckle on back side. | |||
= Tasks to Complete = | = Tasks to Complete = | ||
* | *Finish 3D model of controls in inventor. | ||
*Post all needed parts on the team google doc. page | *Post all needed parts on the team google doc. page | ||
*Figure out control board selection. | |||
= Materials Needed = | = Materials Needed = | ||
*Refer to the team google doc. or the BOM | *Refer to the team google doc. or the BOM |
Revision as of 18:54, 26 January 2013
Attendance
Start time: 10:00 am
End time: ??
Members present: Shayna R., Nick B., Eric A., Gafei S., Vlad B., Matt B., Kyle
Members Attending Next Meeting: ??
Tasks In Progress
- Define functionality on control functions.
- Verify current model dimensions.
- Design dimensions for strap buckle on back side.
Tasks to Complete
- Finish 3D model of controls in inventor.
- Post all needed parts on the team google doc. page
- Figure out control board selection.
Materials Needed
- Refer to the team google doc. or the BOM