2013:Climber 01.30: Difference between revisions
From 1511Wookiee
Jump to navigationJump to search
Mechanical1 (talk | contribs) No edit summary |
Mechanical1 (talk | contribs) No edit summary |
||
Line 26: | Line 26: | ||
* | * | ||
list and order all assembly hardware | list and order all assembly hardware | ||
Line 32: | Line 33: | ||
Alex- Design restraining mechanism for red arms and black arms | Alex- Design restraining mechanism for red arms and black arms | ||
Alex - Add sensors to model | |||
Brianna- Design the cross member with leg guide for Red arms and Black arms | Brianna- Design the cross member with leg guide for Red arms and Black arms | ||
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline | Combine all subteams parts and design the CG to be within +/- one inch from bot centerline | ||
Line 43: | Line 42: | ||
Belay attachment points | Belay attachment points | ||
= Materials Needed = | = Materials Needed = |
Latest revision as of 15:15, 30 January 2013
Attendance
Start time:
End time:
Members present:
Members Attending Next Meeting:
Tasks Completed
- task
- sub-task
- sub-task
- task
Tasks In Progress
- task
- sub-task
- sub-task
- task
Tasks to Complete
list and order all assembly hardware
Design release mechanism for red arms and black arms
Alex- Design restraining mechanism for red arms and black arms
Alex - Add sensors to model
Brianna- Design the cross member with leg guide for Red arms and Black arms
Combine all subteams parts and design the CG to be within +/- one inch from bot centerline
Use cross members to strengthen the elevator shafts
Belay attachment points
Materials Needed
- task
- sub-task
- sub-task
- task