2009:Integration 1.20.2009: Difference between revisions

From 1511Wookiee
Jump to navigationJump to search
(adding notes)
 
m (stupid paste)
Line 1: Line 1:
'''Integration Meeting 1.20.2009'''
'''Integration Meeting 1.20.2009'''  


<u>'''Status Updates'''</u>
<u>'''Status Updates'''</u>  


Mech1&amp;2 – Made progress, not as far as they wanted to be… hoping to be done Thursday, latest Sunday. Sensors, Motors &amp; Frame to be worked tonight.  
Mech1&amp;2 – Made progress, not as far as they wanted to be… hoping to be done Thursday, latest Sunday. Sensors, Motors &amp; Frame to be worked tonight.  
Line 13: Line 13:
Drivetrain – working on bumpers, waiting for return of frame  
Drivetrain – working on bumpers, waiting for return of frame  


Field Crate – Needs to add tops to trailers, build fueling stations &amp; orbit balls
Field Crate – Needs to add tops to trailers, build fueling stations &amp; orbit balls  


<br>
<br>  


<u>'''Issues'''</u>
<u>'''Issues'''</u>  


Mechanical needs to know which sensors – its on the Wiki, just needed to know where.  
Mechanical needs to know which sensors – its on the Wiki, just needed to know where.  
Line 29: Line 29:
Drivetrain needs to fix rubbing wheel for programming  
Drivetrain needs to fix rubbing wheel for programming  


Mouse needs Mounting Design BOM – Need to start updating  
Mouse needs Mounting Design  
 
BOM – Need to start updating  


Do we need front wheels? Drivetrain needs from Mechanical  
Do we need front wheels? Drivetrain needs from Mechanical  

Revision as of 09:07, 21 January 2009

Integration Meeting 1.20.2009

Status Updates

Mech1&2 – Made progress, not as far as they wanted to be… hoping to be done Thursday, latest Sunday. Sensors, Motors & Frame to be worked tonight.

Electrical – Finished choosing sensors, worked on Mouse for distance traveling

Electrical Controls – Sheet metal box is being designed up, pinouts are posted

Programming – tested upper mechanism code, autonomous has written pseudo code, drive code should be done this week

Drivetrain – working on bumpers, waiting for return of frame

Field Crate – Needs to add tops to trailers, build fueling stations & orbit balls


Issues

Mechanical needs to know which sensors – its on the Wiki, just needed to know where.

Mechanical needs to know how much detail is needed for frame (Amy/Josh)

Electrical needs mechanical mounting for mouse

Programming would like to see if there is a way to get weight distribution on chasis

Drivetrain needs to fix rubbing wheel for programming

Mouse needs Mounting Design

BOM – Need to start updating

Do we need front wheels? Drivetrain needs from Mechanical

Surfaces for control system mounting should be done today

Available space of inventor mock up - complete

Need to know what sensors are needed - complete

Trap doors defined – pretty much done, need other teams to review

Need control box I/O’s – complete pending

Encoder wheel needed? – Yes

Needed Mouse going to be used

Need help porting ProE – still a need