2011:Drivetrain 2.1
From 1511Wookiee
Jump to navigationJump to search
Attendance
Start time:
End time:
Members present:
Members Attending Next Meeting:
Tasks Completed
- Drive train is complete with wheels, spacers and chain tensioned. 3/4" wood cut for bumpers. Front and rear pieces cut 5" high by 28.5", side pieces cut 5" high by 37". Mounting points are in the center of the channel frame 3/8" dia holes. Bottom edge of the wood is 1.375" off the floor.
- Using oversize channel (1.25" ID) sections as capture the frame channel and act as washers. These sections stay with the bumpers and add no weight to the robot.
- sub-task
- task
Tasks In Progress
- task
- sub-task
- sub-task
- task
Tasks to Complete
- anchor the "T" nuts in the wood and glue the pool noodles
- Front and rear have not been drilled waiting for final arm achcor points to be determined
- sub-task
- task
Materials Needed
- task
- sub-task
- sub-task
- task