02.04.2010

Start time:6:30

End time:

Members present: Alex R. Ben S. Matt M. Lizzy

Members Attending Next Meeting:

Tasks Completed:

  • Basic assemble complete
  • Electrical board screwed on and hooked up
  • Handed over to programming


Tasks In Progress:

  • n/a - Ben is helping with controls, Lizzy, Alex, and Tom Cavaliere are inventorying new parts, and Matt is updating the wiki.


Tasks to Complete:

  • Get the robot back
  • Final assembly - still waiting on ball guard


Materials Needed:

  • The last few parts

Do not forget to add your needed items to the Shopping List!!