Date: 2/1/09

Start Time: 11:00 AM

End Time: 4:30 PM

Members Present: Nick, (Eric)

Tasks Completed:

1. Assembled parts of the mock controls.

2. Ordered final box parts from McMaster Carr.

Tasks to Complete:

1. Finalize sheet metal modeling.

2. Finish assembling mock controls.