Date: 1/31/09

Start Time: 11:00 AM

End Time: 9:30 PM

Members Present: Nick, Alex, (Eric), (Victor)

Tasks Completed:

1. Incorporated D-rings, latches, and sliders into main control box.

2. Started to assemble secondary controls onto mock control board.

Tasks to Complete:

1. Finalize sheet metal modeling