2011:Controls 2.3

From 1511Wookiee
Revision as of 18:27, 3 February 2011 by ElectricalControls (talk | contribs)
Jump to navigationJump to search

Attendance

Start time: 6PM

End time:

Members present: Crystal, JP, Quinten, Gafei

Members Attending Next Meeting:

Tasks Completed

  • The functional block diagram is completed in electrical form. It is listed below:
    Control wire layout.jpg

Tasks In Progress

  • Schematics need to be draw up for formal wire layout of control undercarriage
    • Addition of potentiometers to paper stencil
    • Publish I/O maps to wiki
  • task

Tasks to Complete

  • Figure out wiring for control system 
    • figure out additional switch functions
    • Figure out method to secure classmate computer
  • Mount preset buttons onto board

Materials Needed

  • Need preset buttons 
    • sheet metal prototype
    • sub-task
  • task