Master Task List
- Design Motor Mounts...Done
- Design Bearing Mounts ...Done
- Help Drivetrain with ProE Import
- Have other teams review Trap Doors - Integration
- Keep Track of Weight Distribution - Integration
- Complete Bill of Materials
- Assign Surfaces for Control System Mounting
- Determine if front wheels are needed
- Choose & Order Materials/Parts
- Create Model Shop Drawings...Week 3 main focus
- Add all belts & pulleys to design
- Define Roller/Chicken Plucker designs ...Done
- Complete Trap Door designs in Inventor
- Define outside material for robot
- Design Sensor Mounts
- Design Battery Box & CRio Mount (Electrical needs help)...Started
- Mock up Weight on the Chassis so programming/Drivers can use
Resources
The 2009 Kit of Parts are designed in Autodesk Inventor Professional and available through the Autodesk FIRSTbase website.
This is the Mechanical Subteam 1's Engineering Notebook
Week 1 - 42 Days Left!!
Week 2 -35 Days Left!!
Week 3 - 28 Days Left!!