Attendance
Start time:
End time:
Members present:
Members Attending Next Meeting:
Tasks Completed
- task
- sub-task
- sub-task
- task
Tasks In Progress
- task
- sub-task
- sub-task
- task
Tasks to Complete
Arm Tasks
- Arm Shaft Machining IN-PROCESS
Drawing completed (Alex W) COMPLETED
* Fabricate Arm/Sprocket Mounting Angles COMPLETED
* Arm Hinge Shaft machining COMPLETED
Drawings complete (TDK) COMPLETED
* Buy or find E-Rings * PENDING
* Layout and Drill Arm Extensions COMPLETED
Partially complete (Jonathan, Manuel)
* Assemble Latches and Springs
Partially complete (Manuel)
Find or make plastic spacers
* Buy #8 button head screws *
* Machine chamfer into Big Sprocket (Tony D)IN-PROCESS
* Bore lightening holes in 66T sprocket ON HOLD
Need drawing
* Mill Arm Slots COMPLETED
In-process (Alex W)
* Deburr Arm Holes COMPLETED
Completed (Lizzy)
* Drill and Tap AndyMark Hub for Arm
Drawing Required
* Assemble AndyMark Hub to Arm
Materials Needed
- Button Head Screws
- 8 x 3/4 long (12 ea)
- 10 x 1/2 long (12 ea)
- task