2009:Field/Crate 2.8.2009

From 1511Wookiee
Jump to navigationJump to search

2/9/09


Time Started: 10:30 am

Time Ended: 8:30 pm


Members Working: Theo, Amy, Kevin, Kim, Leann


Tasks Completed:

  1. Crate handles backed
  2. Panels of airlocks assembled
  3. Front barrier of fueling port assembled
  4. Cross braces made for both crates
  5. Jefferson crate painted (almost done)
  6. Vision targets constructed (waiting for fabric)
  7. Fiberglass tape ordered for rally field
  8. Field rail flanges attached to 4X4s

Tasks Still to do:

  1. Finish painting crates (ours needs some new paint where the plywood was replaced)
  2. Fabric for vision targets -> complete them & install
  3. Assemble alliance station walls
  4. Buy/cut plywood for bottom of alliance station walls
  5. Outposts- What do we want to do- lexan? the seat?
  6. Buy any addition Regolith needed
  7. Buy hardware needed for cross braces on crates