 01.20.2010

Start time: 18:30

End time:

Members present: Crystal, Quintin, Rachel, Fellows

Members Attending Next Meeting: Crystal


Tasks Completed:

  • Mock controls completed and mounted on plywood
  • Mock controls tested for connection: affirmative
  • Quinten modeled the Qslide! (see below)



Tasks In Progress:



Tasks to Complete:




Materials Needed:

  • Buttons ordered
  • CAD Model design fabricated

Do not forget to add your needed items to the Shopping List!!


Images & Additional Updates:

QSlide.JPG