Field
- soccer nets were cut
- Sat through Thursday set up field in cafe. (Friday gym set up)
- Will be painting this weekend
Electrical
- Lexan has been ordered and will come in Monday
- need to build covers
- will convert the BoM into the official format
- need final design for board placement - from mechanical
Controls
- circuit board is almost done and ready to be programmed
- joystick casing sent to Harris to be fabricated
Mechanical (hanger / superstructure)
- winch is in the inventor design and needs to be coupled to the superstructure
- superstructure mat'ls to be integrated in inventor and mat'ls must be purchased
- weights are needed, CG must be calculated
Drive-train
- ball guards exchanged for driveway poles! and clear bumps.
- will drill new holes for the guards
- back ball guard needs to be designed
- poles need to be purchased tonight
Mechanical (Kicker)
- the parts to be made at Ike's shop are all completed
- sheet metal weldments are needed
- need to know the size of the electrical board
- need bumper supports from the drivetrain
- weight and beater bar need to be accounted for - some parts ordered
Programming
- need to know from Mech 1 how the hook is going to be operated and also need and image
Coverage for next week:
Tuesday through Friday - begin at noon - regular close time.
Tuesday - Jeff
Wednesday - Bear
Thursday - Cynette and Terri Mo.
Friday - Sharon, Lee, Dave V.