2011:Field 2/15/2011
Members present: Shayna, Jason, Amy
Members Attending Next Meeting:
Tasks Completed:
Task 1 - Glued reflective tape to the upright poles
Task 2 - Mounted one set of cords for Rally field
Task 3 - Made list of items that need to be completed this weekend prior to rally set-up
Tasks In Progress:
Task 1 - Mounting second set of power cords
Task 2 - Finsih building final shelf in the closet
Tasks to Complete:
Task 1 - Drill holes for rail alignment
Task 2 - Mount post toppers
Task 3 - Determine/Construct method to keep lane dividers in place (on order)
Task 4 - Mounting system on player stations for power/connectivity (1 remaining to make)
Task 5 - Drill holes in each player station for cords
Task 6 - Drill 1 hole in each piece of Lexan for securing
Task 7 - Sensor platefor top of post
Task 8 - Plate to connect rails to alliance walls (on order from Harris)
Materials Needed:
Item 1 -
Item 2 - Remaing bolts that were the wrong size
Images & Additional Updates:
(Make sure you are in the Rich Editor and use the upload file button on the toolbox to the left to upload the file, then insert an image using the button above. Sizing can be done using the length/width pixel size)