2010:Field/Crate: Difference between revisions
FieldCrate (talk | contribs) No edit summary |
m (Field/Crate moved to 2010:Field/Crate) |
||
(4 intermediate revisions by one other user not shown) | |||
Line 5: | Line 5: | ||
#<strike>Complete rest of bumps (12) </strike>1/24 | #<strike>Complete rest of bumps (12) </strike>1/24 | ||
#<strike>Complete Goals and Goal Ramps (4)</strike> 2/2 | #<strike>Complete Goals and Goal Ramps (4)</strike> 2/2 | ||
#Complete ball returns and towers (2) | #<strike>Complete ball returns and towers </strike> (2) | ||
#<strike>Make Tridents (2) </strike>1/23 | #<strike>Make Tridents (2) </strike>1/23 | ||
#Create vision targets (4) | #Create vision targets (4) | ||
#<strike>Look to see if crate or alliance station walls need maintenance or improvment</strike> | #<strike>Look to see if crate or alliance station walls need maintenance or improvment</strike> | ||
#<strike>Verify that the crate dimensions are the same as last year. Determine if we need to alter the crate.''(Our crate is 48" x 48" x 69") | #<strike>Verify that the crate dimensions are the same as last year. Determine if we need to alter the crate.</strike>''(Our crate is 48" x 48" x 69")<br>'' | ||
''4.6.1.All Crates MUST:<br>1. Weigh less than 400 pounds when fully loaded.<br>2. "Sit" on 2 pieces of 4" x 4" lumber, spaced at least 28" apart so it can be moved by a forklift.<br>3. Have a footprint no greater than 4' x 4' and be no taller than 5'10" (70") high. This maximum includes the 4" x 4" lumber mentioned above.<br>4. Be constructed so it can withstand stacking during transport and storage.<br>5. Have “TEAM # XXXX” (insert your team number) painted or stenciled in letters at least 6” high on at least one side of the crate. '' <br> | ''4.6.1.All Crates MUST:<br>1. Weigh less than 400 pounds when fully loaded.<br>2. "Sit" on 2 pieces of 4" x 4" lumber, spaced at least 28" apart so it can be moved by a forklift.<br>3. Have a footprint no greater than 4' x 4' and be no taller than 5'10" (70") high. This maximum includes the 4" x 4" lumber mentioned above.<br>4. Be constructed so it can withstand stacking during transport and storage.<br>5. Have “TEAM # XXXX” (insert your team number) painted or stenciled in letters at least 6” high on at least one side of the crate. '' <br> | ||
Line 23: | Line 23: | ||
#<strike>4 angle pieces for front of goals</strike> 2/2 | #<strike>4 angle pieces for front of goals</strike> 2/2 | ||
#<strike>Create tops for 3 goals</strike> 1/31 | #<strike>Create tops for 3 goals</strike> 1/31 | ||
#Do we have enough soccer balls?(need 12) & ball pump ''Theo will contact Phys. Ed. Dept for loan''<br> | #Do we have enough soccer balls?(need 12) & ball pump ''Theo will contact Phys. Ed. Dept for loan''<br> | ||
#Look at full field current model- | #<strike>Look at full field current model- how to integrate goals- over goal wall with vision targets</strike> | ||
#<strike>Goal netting for sides?</strike> Ordered 1/28 | #<strike>Goal netting for sides?</strike> Ordered 1/28 | ||
#<strike>Lag bolts for tower 4X4s</strike> Ordered 1/28 - McMaster | #<strike>Lag bolts for tower 4X4s</strike> Ordered 1/28 - McMaster | ||
#Determine final connections of bumps, towers, and platforms to carpet and field sides | #Determine final connections of bumps, towers, and platforms to carpet and field sides | ||
#<strike>Cut notches (2) in 4 bumps for tower 4X4 connections </strike>2/6 | #<strike>Cut notches (2) in 4 bumps for tower 4X4 connections </strike>2/6 | ||
#Re-print 4 vision targets | #<strike>Re-print 4 vision targets </strike>2/16 | ||
#''Our versions of the 3 remaining corrals''- Solution: Theo will provide construction fence (orange/plastic)<br> | #<strike>''Our versions of the 3 remaining corrals''- Solution: Theo will provide construction fence (orange/plastic)</strike> 2/9<br> | ||
#<strike>Need lots of strong velcro- hefty Hefty HEFTY</strike> Ordered from Mcmaster 2/4 | #<strike>Need lots of strong velcro- hefty Hefty HEFTY</strike> Ordered from Mcmaster 2/4 | ||
#<strike>Carpet (12) bumps </strike> 2/6 | #<strike>Carpet (12) bumps </strike> 2/6 | ||
#<strike>Wrap foam in spandex</strike> 2/3 | #<strike>Wrap foam in spandex</strike> 2/3 | ||
#<strike>Attache Foam to inside of goals</strike> 2/6 | #<strike>Attache Foam to inside of goals</strike> 2/6 | ||
#Determine Back frame for vision targets | #<strike>Determine Back frame for vision targets</strike> | ||
#<strike>Fix (glue) trident that is currently not attached completely. </strike>2/7 | #<strike>Fix (glue) trident that is currently not attached completely. </strike>2/7 | ||
#Cut soccer netting | #<strike>Cut soccer netting</strike>2/9 | ||
<br> | <br> | ||
= This is the Field/Crate Subteam's Engineering Notebook = | = This is the Field/Crate Subteam's Engineering Notebook = | ||
Line 45: | Line 45: | ||
'''Week 1''' | '''Week 1''' | ||
2010:FieldCrate 01:10<br>2[[2010:FieldCrate 01:12|010:FieldCrate 01:12]]<br>[[2010:FieldCrate 01:13]]<br>[[2010:FieldCrate 01:14]]<br>[[2010:FieldCrate 01:16]]<br>[[2010:FieldCrate 01:17]]<br> | 2010:FieldCrate 01:10<br>2[[2010:FieldCrate 01:12|010:FieldCrate 01:12]]<br>[[2010:FieldCrate 01:13]]<br>[[2010:FieldCrate 01:14]]<br>[[2010:FieldCrate 01:16]]<br>[[2010:FieldCrate 01:17]]<br> | ||
'''Week 2'''<br>[[2010:FieldCrate 01:19]]<br>[[2010:FieldCrate 01:20]]<br>[[2010:FieldCrate 01:21]]<br>[[2010:FieldCrate 01:23]]<br>[[2010:FieldCrate 01:24]]<br> | '''Week 2'''<br>[[2010:FieldCrate 01:19]]<br>[[2010:FieldCrate 01:20]]<br>[[2010:FieldCrate 01:21]]<br>[[2010:FieldCrate 01:23]]<br>[[2010:FieldCrate 01:24]]<br> | ||
'''Week 3''' | '''Week 3''' |
Latest revision as of 15:47, 14 November 2010
Master Task List
Complete 1 bump, 1 platform, and 1 tower for team testingPurchase rest of materials for ball returns, carpet for bumps, foam for goals, wood for goalsComplete rest of bumps (12)1/24Complete Goals and Goal Ramps (4)2/2Complete ball returns and towers(2)Make Tridents (2)1/23- Create vision targets (4)
Look to see if crate or alliance station walls need maintenance or improvmentVerify that the crate dimensions are the same as last year. Determine if we need to alter the crate.(Our crate is 48" x 48" x 69")
4.6.1.All Crates MUST:
1. Weigh less than 400 pounds when fully loaded.
2. "Sit" on 2 pieces of 4" x 4" lumber, spaced at least 28" apart so it can be moved by a forklift.
3. Have a footprint no greater than 4' x 4' and be no taller than 5'10" (70") high. This maximum includes the 4" x 4" lumber mentioned above.
4. Be constructed so it can withstand stacking during transport and storage.
5. Have “TEAM # XXXX” (insert your team number) painted or stenciled in letters at least 6” high on at least one side of the crate.
Make sure the crate still has the applicable shelves.Shelves are in the closet
1/26 Additions:
Determine carpetPurchased 1/30/10Determine coefficient of friction of spandex vs foam by its selfSpandex will be used 1/30/10Create shopping list for ball returnsMaterial bought on McMaster 1/28 and at Home Depot 1/30Assemble last goal front ramp1/264 angle pieces for front of goals2/2Create tops for 3 goals1/31- Do we have enough soccer balls?(need 12) & ball pump Theo will contact Phys. Ed. Dept for loan
Look at full field current model- how to integrate goals- over goal wall with vision targetsGoal netting for sides?Ordered 1/28Lag bolts for tower 4X4sOrdered 1/28 - McMaster- Determine final connections of bumps, towers, and platforms to carpet and field sides
Cut notches (2) in 4 bumps for tower 4X4 connections2/6Re-print 4 vision targets2/16Our versions of the 3 remaining corrals- Solution: Theo will provide construction fence (orange/plastic)2/9Need lots of strong velcro- hefty Hefty HEFTYOrdered from Mcmaster 2/4Carpet (12) bumps2/6Wrap foam in spandex2/3Attache Foam to inside of goals2/6Determine Back frame for vision targetsFix (glue) trident that is currently not attached completely.2/7Cut soccer netting2/9
This is the Field/Crate Subteam's Engineering Notebook
Week 1
2010:FieldCrate 01:10
2010:FieldCrate 01:12
2010:FieldCrate 01:13
2010:FieldCrate 01:14
2010:FieldCrate 01:16
2010:FieldCrate 01:17
Week 2
2010:FieldCrate 01:19
2010:FieldCrate 01:20
2010:FieldCrate 01:21
2010:FieldCrate 01:23
2010:FieldCrate 01:24
Week 3
2010:FieldCrate 01:26
2010:FieldCrate 01:27
2010:FieldCrate 01:28
2010:FieldCrate 01:30
2010:FieldCrate 01:31
Week 4
2010:FieldCrate 02:02
2010:FieldCrate 02:03
2010:FieldCrate 02:04
2010:FieldCrate 02:06
2010:FieldCrate 02:07
Week 5
2010:FieldCrate 02:09
2010:FieldCrate 02:10
2010:FieldCrate 02:11
2010:FieldCrate 02:13
2010:FieldCrate 02:14
Week 6
2010:FieldCrate 02:16
2010:FieldCrate 02:17
2010:FieldCrate 02:18
2010:FieldCrate 02:20
2010:FieldCrate 02:21