= Master Task List  =
= Master Task List  =


#<strike>Complete 1 bump, 1 platform</strike>, and 1 tower for team testing  
#<strike>Complete 1 bump, 1 platform</strike><strike>, and 1 tower for team testing</strike>
#<strike>Purchase rest of materials for ball returns, carpet for bumps, foam for goals, wood for goals</strike>&nbsp;  
#<strike>Purchase rest of materials for ball returns, carpet for bumps, foam for goals, wood for goals</strike>&nbsp;  
#<strike>Complete rest of bumps (12) </strike>1/24  
#<strike>Complete rest of bumps (12) </strike>1/24  
Line 8: Line 8:
#<strike>Make Tridents (2) </strike>1/23  
#<strike>Make Tridents (2) </strike>1/23  
#Create&nbsp;vision targets (4)&nbsp;  
#Create&nbsp;vision targets (4)&nbsp;  
#<strike>Look to see if crate or alliance station walls need maintenance or improvment</strike>
#<strike>Look to see if crate or alliance station walls need maintenance or improvment</strike>  
#Verify that the crate dimensions are the same as last year.&nbsp; Determine if we need to alter the crate.  
#Verify that the crate dimensions are the same as last year.&nbsp; Determine if we need to alter the crate.  
#<strike>Make sure the crate still has the applicable shelves. </strike>Shelves are in the closet
#<strike>Make sure the crate still has the applicable shelves. </strike>Shelves are in the closet
Line 25: Line 25:
#<strike>Lag bolts for tower 4X4s</strike>&nbsp; Ordered 1/28 - McMaster  
#<strike>Lag bolts for tower 4X4s</strike>&nbsp; Ordered 1/28 - McMaster  
#Determine final connections of bumps, towers, and platforms to carpet and field sides  
#Determine final connections of bumps, towers, and platforms to carpet and field sides  
#Cut notches (2) in 4 bumps for tower 4X4 connections  
#<strike>Cut notches (2) in 4 bumps for tower 4X4 connections </strike>2/6
#Re-print 4 vision targets  
#Re-print 4 vision targets  
#''Our versions of the 3 remaining corrals''- Solution: Theo will provide construction fence (orange/plastic)<br>  
#''Our versions of the 3 remaining corrals''- Solution: Theo will provide construction fence (orange/plastic)<br>  
#Need lots of strong velcro- hefty Hefty HEFTY  
#<strike>Need lots of strong velcro- hefty Hefty HEFTY</strike> Ordered from Mcmaster 2/4
#Carpet (12) bumps  
#<strike>Carpet (12) bumps&nbsp;</strike> 2/6
#<strike>Wrap foam in spandex</strike>&nbsp; 2/3  
#<strike>Wrap foam in spandex</strike>&nbsp; 2/3  
#Attache Foam to inside of goals  
#<strike>Attache Foam to inside of goals</strike> 2/6
#Determine Back frame for vision targets  
#Determine Back frame for vision targets  
#Fix (glue) trident that is currently not attached completely.
#Fix (glue) trident that is currently not attached completely.

Revision as of 19:20, 6 February 2010

Master Task List

  1. Complete 1 bump, 1 platform, and 1 tower for team testing
  2. Purchase rest of materials for ball returns, carpet for bumps, foam for goals, wood for goals 
  3. Complete rest of bumps (12) 1/24
  4. Complete Goals and Goal Ramps (4) 2/2
  5. Complete ball returns and towers  (2)
  6. Make Tridents (2) 1/23
  7. Create vision targets (4) 
  8. Look to see if crate or alliance station walls need maintenance or improvment
  9. Verify that the crate dimensions are the same as last year.  Determine if we need to alter the crate.
  10. Make sure the crate still has the applicable shelves. Shelves are in the closet

1/26 Additions:

  1. Determine carpet Purchased 1/30/10
  2. Determine coefficient of friction of spandex vs foam by its self  Spandex will be used 1/30/10
  3. Create shopping list for ball returns Material bought on McMaster 1/28 and at Home Depot 1/30
  4. Assemble last goal front ramp 1/26
  5. 4 angle pieces for front of goals 2/2
  6. Create tops for 3 goals 1/31
  7. Do we have enough soccer balls?(need 12) & ball pump
  8. Look at full field current model- how to integrate goals- over goal wall with vision targets
  9. Goal netting for sides? Ordered 1/28
  10. Lag bolts for tower 4X4s  Ordered 1/28 - McMaster
  11. Determine final connections of bumps, towers, and platforms to carpet and field sides
  12. Cut notches (2) in 4 bumps for tower 4X4 connections 2/6
  13. Re-print 4 vision targets
  14. Our versions of the 3 remaining corrals- Solution: Theo will provide construction fence (orange/plastic)
  15. Need lots of strong velcro- hefty Hefty HEFTY Ordered from Mcmaster 2/4
  16. Carpet (12) bumps  2/6
  17. Wrap foam in spandex  2/3
  18. Attache Foam to inside of goals 2/6
  19. Determine Back frame for vision targets
  20. Fix (glue) trident that is currently not attached completely.


This is the Field/Crate Subteam's Engineering Notebook

Week 1

2010:FieldCrate 01:10
2010:FieldCrate 01:12
2010:FieldCrate 01:13
2010:FieldCrate 01:14
2010:FieldCrate 01:16
2010:FieldCrate 01:17

Week 2
2010:FieldCrate 01:19
2010:FieldCrate 01:20
2010:FieldCrate 01:21
2010:FieldCrate 01:23
2010:FieldCrate 01:24

Week 3

2010:FieldCrate 01:26
2010:FieldCrate 01:27
2010:FieldCrate 01:28
2010:FieldCrate 01:30
2010:FieldCrate 01:31

Week 4

2010:FieldCrate 02:02
2010:FieldCrate 02:03
2010:FieldCrate 02:04
2010:FieldCrate 02:06
2010:FieldCrate 02:07

Week 5

2010:FieldCrate 02:09
2010:FieldCrate 02:10
2010:FieldCrate 02:11
2010:FieldCrate 02:13
2010:FieldCrate 02:14

Week 6

2010:FieldCrate 02:16
2010:FieldCrate 02:17
2010:FieldCrate 02:18
2010:FieldCrate 02:20
2010:FieldCrate 02:21

Engineering Notebook Templates are available at: Engineering_Notebook_Template
Please Label all pages 2010:FieldCrate XX.XX to avoid Confusion!!

Archives