01.11.2009

Start time: 11

End time:

Members present: Rika, Michael, Crystal, Dave, Karen, Victor


Tasks Completed:

  • Finished Electrical Mock board  with 4 Victors
  • Converted CIM motors to PWM connetions
  • Encoded CIMs



Tasks In Progress:

  • Assembly on drivetrain
  • Battery charging ^_~



Tasks to Complete:

  • task
  • task



Images & Additional Updates:

(Use the upload file button on the toolbox to the left to upload the file, then insert an image using the button above.  Sizing can be done using the length/width pixel size)