2011:Field 1/20/2011: Difference between revisions
m (Field 1/20/2011 moved to 2011:Field 1/20/2011) |
FieldCrate (talk | contribs) No edit summary |
||
Line 1: | Line 1: | ||
Members present: | Members present: Jason, Manuel, Kieran, Shayna | ||
Mentors present: Amy, Lloyd | |||
<br>Members Attending Next Meeting: | <br>Members Attending Next Meeting: | ||
Line 7: | Line 9: | ||
-------------------------------------------------------------------------------- | |||
-------------------------------------------------------------------------------- | |||
Tasks Completed: | Tasks Completed: | ||
Task 1 - | Task 1 - Interference fit the end plates onto pegs.<br>Task 2 - Cut 2x4s for player station walls. <br>Task 3 - Assemble 4 stop plates for tower assemblies. <br> | ||
-------------------------------------------------------------------------------- | |||
<br>-------------------------------------------------------------------------------- | |||
Tasks In Progress: | Tasks In Progress: | ||
Task 1 - | Task 1 - Assemble 3 more tower assemblies. | ||
Task 2 - | Task 2 - | ||
-------------------------------------------------------------------------------- | |||
Tasks to Complete: | Tasks to Complete: | ||
Task 1 - | Task 1 - Assemble 4 stop plates to poles. | ||
Task 2 - Determine reflective tape part number and who we can buy it from. <br>Task 3- Cut pieces for player stations table. | |||
Task 4 - Paint player station walls. | |||
Task 5 - Paint field elements. | |||
Line 41: | Line 61: | ||
Materials Needed: | Materials Needed: | ||
<br>Item 1 - | <br>Item 1 - Field tape. | ||
Item 2 - Game pieces. | |||
Item 3 - Reflective Tape. | |||
Item 4 - Hardware for player station walls, velcro. | |||
---- | ---- | ||
Images & Additional Updates: | Images & Additional Updates: | ||
(Make sure you are in the Rich Editor and use the upload file button on the toolbox to the left to upload the file, then insert an image using the button above. Sizing can be done using the length/width pixel size) | (Make sure you are in the Rich Editor and use the upload file button on the toolbox to the left to upload the file, then insert an image using the button above. Sizing can be done using the length/width pixel size) |
Revision as of 05:39, 21 January 2011
Members present: Jason, Manuel, Kieran, Shayna
Mentors present: Amy, Lloyd
Members Attending Next Meeting:
Tasks Completed:
Task 1 - Interference fit the end plates onto pegs.
Task 2 - Cut 2x4s for player station walls.
Task 3 - Assemble 4 stop plates for tower assemblies.
--------------------------------------------------------------------------------
Tasks In Progress:
Task 1 - Assemble 3 more tower assemblies.
Task 2 -
Tasks to Complete:
Task 1 - Assemble 4 stop plates to poles.
Task 2 - Determine reflective tape part number and who we can buy it from.
Task 3- Cut pieces for player stations table.
Task 4 - Paint player station walls.
Task 5 - Paint field elements.
Materials Needed:
Item 1 - Field tape.
Item 2 - Game pieces.
Item 3 - Reflective Tape.
Item 4 - Hardware for player station walls, velcro.
Images & Additional Updates:
(Make sure you are in the Rich Editor and use the upload file button on the toolbox to the left to upload the file, then insert an image using the button above. Sizing can be done using the length/width pixel size)